PROJECT UPDATE: COLCHESTER NORTHERN GATEWAY – SOUTH (CNGS)

Works are progressing well on site, with the archaeology team starting today!

Breheny Team led by Keiran Eastell (Sub Agent) and Richard Pelling (Project Manager) are currently working on the deep drainage (over 7 metres) in preparation for The Walk and are planning to start phase 2 of our works next week. This will involve accessing the Eastern Basin and the area at the Archery Club to allow for earthworks and completion of the foul water drainage. The area at the Rugby Club will fall under phase 2 of the works and this section is due to commence on the 11th September 2020.

We have been working collaboratively with Colchester Amphora Trading Ltd  (CATL) to ensure we are delivering as per our agreed programme. Yesterday, Keiran walked through our progress with Jack Conington from CATL and Michael Woods from Colchester Amphora Energy Ltd (CAEL).