IVC Facility - Donarbon Waste, Waterbeach
IVC Facility - Donarbon Waste, Waterbeach - Main ImageIVC Facility - Donarbon Waste, Waterbeach - Thumb 1IVC Facility - Donarbon Waste, Waterbeach - Thumb 2IVC Facility - Donarbon Waste, Waterbeach - Thumb 3
Approx.Value: £1.5
Contract Period: 61 weeks

Description of works:

Works are being undertaken in two stages.

Stage 1
For site preparation and includes dynamic compaction, excavation and filling.

Stage 2
Groundworks and concrete hardstandings to composting facility and will include:

• Drainage
• Sub base
• Ground slab
• Foundations
• Piling and ground-slab to reception building
• 20nr tunnel base foundations
• Office building foundations